Single sourcing: what happens when you rely on one supplier?

Relying on a single supplier is rarely a deliberate choice. How to find your risky items, and when a qualified backup supplier is enough.

ProcurePro 5 min read

Split illustration: on the left a breaking chain, falling dominoes and people running; on the right several intertwined supply routes around a shield, between factories and warehouses

Since 2020, every business leader has seen what happens when a supplier suddenly cannot deliver. Even so, many companies in Central Europe still buy their most critical items from a single source.

This is rarely the result of a deliberate decision. It usually builds up over years, and nobody notices as long as everything works. In this article we look at where the problem comes from, how to find it in your own portfolio, and what to do about it.

How does an item end up with one supplier?

When we ask in our procurement projects why a critical item has only one source, we hear almost the same answers every time:

  • “The relationship has been good for years, why switch?” The supplier is reliable, communication works, there are no complaints.
  • “The others are 5–10% more expensive.” A second quote was requested at some point, then set aside until there would be time to look again.
  • The specification was built around the supplier’s product. The drawings, tolerances and material codes describe their solution, so another manufacturer’s part cannot be used without a new approval.
  • The volume discount would be lost. Splitting the volume between two sources raises the unit price at both.
  • It is nobody’s priority. As long as it works, it never makes the agenda.

All of these are understandable. The problem is that in none of them did anyone assess what happens if the supplier drops out.

What happens when the supplier drops out?

A flood at the supplier’s site. A bankruptcy. A geopolitical event that cuts the transport route. Or simply the supplier moving capacity to a bigger customer.

On the buyer’s side, production stops, your own delivery dates slip, penalties and expedited freight costs appear, and procurement spends weeks firefighting. On top of the direct damage comes the loss of your own customers’ trust, which is hard to put a number on but lasts a long time.

Five steps to a deliberate supplier strategy

1. Identify your single-source risks

One question is enough: if this supplier dropped out tomorrow, how many weeks would it take us to replace them?

Go through your active suppliers and answer it for each one. If the answer is more than four weeks, that item is a risk. Bring in engineering, because they know how long it takes to approve a new part.

2. Prioritize with the Kraljic matrix

Not every single-source item is equally dangerous. The Kraljic matrix helps decide where to act. In the bottleneck and strategic categories you should never rely on a single source. For non-critical items, one supplier can even be an advantage, because it means less admin.

3. Plan the second source as a project

Finding a new supplier, auditing them, producing samples and getting approval does not happen overnight. For critical parts this is typically a 12–18 month project. That is why it pays to start now, not when your current supplier has already flagged a problem.

Treat it as a real project, with an owner, a schedule and a budget. Without engineering, quality and production on board it will stall.

4. Sometimes a qualified backup is enough

You do not always have to split the volume between two suppliers. In some cases a qualified backup supplier is enough: a company you do not actively order from, but whose product is approved and who could start delivering within four weeks.

This keeps the volume discount with your main supplier while still reducing the risk. Place a small trial order with the backup once a year so the approval does not go stale.

5. Put a cost on the risk

The “cheaper” single source is not cheaper once you add the expected cost of the risk. A simple estimate: how much damage would an outage cause, and how likely is it within a given period? Compare that figure with the cost of building a second source, and the decision often becomes obvious.

We cover the full-cost view in detail in our article on total cost of ownership.

What to ask your current supplier

Building a second source does not have to damage the relationship with your current supplier. In fact, part of the risk can be reduced together with them. In an open conversation, ask about the following:

  • Do they have a business continuity plan? What happens if their production line or site goes down? Do they have another site that could also make your product?
  • Where do they source their critical materials? Often the single source is not your direct supplier but their supplier. If there is only one manufacturer at that level, it affects you too.
  • How much stock of your product do they hold? An agreed safety stock at the supplier or in your own warehouse can buy weeks in an outage.
  • How will they notify you of a problem? Agree who informs whom, and how far in advance, when a capacity or material shortage is expected.

A good supplier is happy to answer these questions, because it is in their interest too that their customer does not have to look urgently for another source.

Common mistakes

  • Only prices are compared. The alternative quote is 5–10% higher, so it is rejected, and nobody puts the risk next to it.
  • The second source exists only on paper. There is a name on the list, but their product never went through approval.
  • The specification never changes. As long as the drawing describes one manufacturer’s solution, a second source cannot come in. It is worth checking whether the part can be designed around a standard solution available from several makers.
  • The assessment is done once. The portfolio changes, and so does the supplier market. The risk list needs updating at least once a year.

Single sourcing is not always wrong

Deliberate single sourcing is fine. If the company knows the risk, has assessed the consequences and accepts them, or has a plan for an outage, that is a legitimate business decision. Single sourcing that nobody is aware of is always a risk.

Do you know right now how many of your critical items depend on one supplier?

How we help

Assessing single-source risk starts with a review of your supplier portfolio and runs through to qualifying the second source. We do this work with 41 years of combined multinational procurement experience. See our procurement service, or request a free consultation.

FAQ

What people often ask.

What is the difference between single sourcing and sole sourcing?

With sole sourcing, only one supplier on the market can make the item, so there is no choice. With single sourcing, alternatives exist, but the company still uses one source. The second case is more common, and it can be changed.

Is it always bad for an item to have one supplier?

No. For non-critical items that are easy to switch, one supplier can mean less admin and a better price. The problem starts when the item is critical and nobody knows what would happen if the supplier dropped out.

How much does it cost to qualify a second supplier?

It depends on the item: samples, testing, audits, possibly tooling. Compare that cost with the damage it would cause if your current supplier could not deliver for several weeks.

Who should own single-source risks?

Procurement leads the assessment, but engineering and production need to be part of the decision. They know the specification, and they can say how much time and work it would take to approve a new source.

All articles →
Split illustration: on the left a flustered team arguing at a messy table, on the right a calm negotiation with a laptop and the negotiation steps shown with Hungarian labels in the background

Procurement negotiation is not an inborn talent but a learnable profession. What professional negotiators do differently, and how to develop your team.