Long lead times are not only the supplier's doing. Five practical steps, from forecasting to your own approval process, that cut them down.
ProcurePro 5 min read
Twelve months. That is how long one of our clients had to wait for a special hydraulic valve, and their whole project slipped because of it.
Long lead times have become normal in many industries over the past few years. That does not mean procurement can do nothing about them. Our experience is that lead times can rarely be eliminated, but they can almost always be shortened. The first step is understanding where they come from.
Behind the number a supplier quotes there are usually several causes at once:
The supplier controls the first four causes. You control the fifth. There is room to move on the supplier side too, once procurement sets up the right conditions.
Supplier lead times are often long because every order comes as a surprise. The supplier cannot reserve capacity or pre-order raw material, so it plans for the worst case.
With a rolling 6–12 month forecast, the supplier can schedule production in advance. We have seen this cut lead times by 20–30%. The forecast does not need to be perfect. What matters is that it is updated regularly and the supplier knows how far it can rely on it.
“We need 2,000 units this year and will call off 100–300 a month.” With an agreement like this the supplier can plan, and you stay flexible on monthly quantities. Both sides benefit.
In the framework agreement, set out:
The “lean everything” approach no longer holds for every item. Some components are worth keeping in stock when their lead time is too long for production to wait.
Calculate the decision item by item. On one side is the cost of holding stock: tied-up capital, warehouse space, the risk of obsolescence. On the other is the cost of a day of downtime or project delay if the item does not arrive on time. For items in the bottleneck quadrant of the Kraljic matrix, the calculation usually comes out in favor of stock.
A backup supplier receives no regular orders, but it is qualified. If the main supplier drops out, or its lead time gets out of control, deliveries from the backup can start within 4–8 weeks.
Qualification can take 6–12 months, so it should not start after the problem has already hit. Once it is done, you have somewhere to turn. If a critical item has only one source today, read our article on the risks of single sourcing as well.
Measure how much time passes between a purchase requisition and the purchase order going out. If it is 4–6 weeks, then a month and a half of the “12-month lead time” is spent inside your own company.
This is usually where results come sooner than at the supplier, because every step is in your hands. The typical causes:
The supplier usually quotes a single number of weeks. That number is really several stages, and each one can be discussed separately:
Ask the supplier for this breakdown and you will see where there is room to move. If raw material is the long part, a forecast or a raw material pre-order helps. If it is the wait for a production slot, a framework agreement and reserved capacity. If it is transport, look at another shipping mode or a warehouse closer to you.
Blaming only the supplier. If procurement does not measure its own internal lead time, it will not see that part of the delay is created in-house.
Stocking everything. Stock costs money. It only makes sense where the cost of a shortage justifies it.
Sending the forecast once. A supplier cannot plan capacity from a number that is six months old. The forecast needs a monthly update.
A backup supplier qualified only on paper. If it never gets a single trial order after qualification, it may not be able to deliver when it counts.
Shortening lead times is joint work between procurement, planning and production. With 41 years of combined multinational procurement experience, we help you find where the time really goes and which tool works for your items. See our procurement service, or request a free consultation.
The supplier quotes the time from purchase order to delivery. The internal requester counts from the moment the need arises to the moment the goods arrive. Measure both, because the gap between the two numbers is spent inside your own process.
Enough to cover consumption during the lead time, plus a safety buffer for delays. The exact quantity depends on how much consumption fluctuates and how reliably the supplier meets its delivery dates.
Ask what form would work for them. Many suppliers plan ahead if part of the volume is a firm call-off commitment, or if the buyer agrees to pre-order raw material. If neither works, start looking for a backup source.
For critical, single-source items, yes. To keep the qualification real rather than on paper, give the backup supplier at least one small trial order a year.
Myth or reality
Procurement negotiation is not an inborn talent but a learnable profession. What professional negotiators do differently, and how to develop your team.
Hackett Group's 2025 benchmark shows top procurement organizations run at lower cost and deliver more savings. What can your team take from it?