Nearshoring and reshoring: where does Europe stand in 2026?

Moving production closer is now a real decision, but it is not free. What recent data shows, what we see in the region, and what to plan for if you decide now.

ProcurePro 5 min read

Infographic map with Poland, the Czech Republic, Hungary and Romania highlighted, arrows showing production moving into the region, and icons with Hungarian labels for manufacturing capacity, cost savings, workforce and supplier network

Five years ago nearshoring was mostly a conference topic. In 2026 it is a concrete decision about where the next plant goes and where the parts will come from.

Many of our clients are affected: manufacturers, automotive and machinery suppliers. In this article we sum up what recent data shows, what we see in the region, and what anyone deciding now should expect.

What does the recent data show?

Capgemini’s reindustrialization report, published in April 2026, surveyed 1,208 executives at large companies in the US, the UK and continental Europe (France, Germany, Italy, the Netherlands, the Nordics and Spain). Among continental European companies it found:

  • friendshoring, locating in allied countries, was cited by 64% of organizations,
  • nearshoring fell from its 2025 level, from 55% to 39%,
  • reshoring, bringing production home, rose from 34% to 42%.

According to the report, talent shortages are a constraint for a large majority of companies, most acutely in advanced manufacturing engineering, automation and digital skills.

Two things follow. First, companies have not given up on moving production, but they have become more selective. The report describes reindustrialization as entering a more selective, strategic phase: companies weigh more carefully where they move and why. Second, the main bottleneck is not capital but skilled labor.

What we see in the region

From a Central European perspective this is tangible. Poland, the Czech Republic, Hungary and Romania have gained new plants and new supplier capacity in recent years. With that, pressure has grown on the labor market and on suppliers.

For a local supplier this is an opportunity: new customers, larger volumes. For a local manufacturer it is also a challenge, because it competes with the newcomers for the same specialists and the same supplier capacity.

Nearshoring is not free

What we hear from almost every client who takes it on:

  • The cost advantage is often 15–25%, not 50%. Many expected far larger savings compared with sourcing from Asia. Shorter transport and lower inventory are real benefits, but labor in the region costs more than in Asia.
  • Labor shortages in critical trades are severe. CNC operators, welders, mechatronics fitters, quality inspectors: there is competition for these roles, which pushes wages up.
  • Building a supplier base takes 18–24 months, not 6. Suppliers have to be found, qualified, samples approved, series production ramped up. Any of these steps can slip.
  • Logistics savings only come with a genuinely short chain. If the plant moves to Hungary but a third of the parts still arrive from Asia, most of the transport risk and inventory need remains.

What this means in practice

1. Plan with a realistic timeline

If you decide on nearshoring now, plan for a go-live in 2027–2028, not next quarter. A deadline that is too short leads the company to pick the first available supplier, not the best one.

2. Do not move everything closer

A good strategy is not “everything local”. For critical parts a nearby source reduces risk; for standard items available from many places, global sourcing is often still better. The Kraljic matrix helps decide which item belongs where.

3. Digitalize as you relocate

The real winners will be those who do not just move production but rebuild their procurement and logistics processes along the way. A new site is a rare chance to start without old habits, with clean data and a modern system.

What this means for local suppliers

If you are a supplier, nearshoring can bring new customers, but only if your company is easy to choose. Manufacturers arriving in the region want to find qualified sources fast, and they pick the one with the least uncertainty.

  • Have your certifications in order. In automotive, for example, certification to the IATF 16949 quality management standard is an entry requirement for many customers.
  • Know your free capacity. The customer’s first question will be what volume you can take on, and from when.
  • Be able to price transparently. If the customer works with a should-cost model, an offer broken down by cost element builds trust.
  • Be digitally reachable. Electronic order intake, delivery confirmations, quality data: international customers expect these.

Steps before a nearshoring decision

  1. Assess your current supply chain. Which parts come from far away, what are the lead times, and where have there been disruptions in recent years?
  2. Calculate the total cost. Do not compare unit prices only, but transport, duties, inventory and quality risk too.
  3. Map the regional supplier market. How many real alternatives exist, and do they have free capacity?
  4. Plan for labor. Where will the specialists come from, and what will they cost?
  5. Build a schedule with qualification and buffer time. Supplier qualification and ramp-up cannot be shortened at will.
  6. Decide up front how success will be measured. Total cost, lead time, inventory level, defect rate: record the baseline values so that after the transition you can measure whether it paid off.

Common mistakes

  • Comparing labor cost only. In the total cost, transport, inventory and quality often matter more.
  • Building the new chain on a single supplier. Proximity does not reduce single-source risk, which we cover in our article on the risks of single sourcing.
  • Launching it as a project without an owner. Nearshoring is a transformation that runs for years, and it needs an owner and a schedule.

If you are facing a nearshoring decision

A relocation succeeds or fails on how thoroughly the supplier market and the total cost are assessed up front. With 41 years of combined multinational procurement experience, we help assess the supplier base, qualify suppliers and manage the transition. See our procurement service, or request a free consultation.

FAQ

What people often ask.

What is the difference between nearshoring, reshoring and friendshoring?

Reshoring is when a company brings production back to its home country. Nearshoring is when it moves production to a nearby country, for example from Western to Central Europe. Friendshoring is when it locates production in countries with close political and economic ties.

How long does it take to build a new supplier base in the region?

In our experience, typically 18–24 months, not six. Finding suppliers, qualifying them, approving samples and ramping up series production happen step by step, and every step can slip.

Should every part be moved closer?

No. For critical, high-risk parts a nearby source reduces risk. For standard items available from many places, global sourcing is often still cheaper, and its risk is manageable.

Where should a company considering nearshoring start?

With an assessment of its current supply chain: which parts come from far away, how critical each one is, and what their total sourcing cost is including transport, duties and inventory. That shows where a switch pays off.

All articles →
Split illustration: on the left a flustered team arguing at a messy table, on the right a calm negotiation with a laptop and the negotiation steps shown with Hungarian labels in the background

Procurement negotiation is not an inborn talent but a learnable profession. What professional negotiators do differently, and how to develop your team.

19 October 2026 · 5 min read
Let's talk

Let's look at your situation.

A free 30-minute call — then you decide. No sales process, no obligation.